| Project Profile
Welding Proves Challenging
On Äsgard-Europipe 11 Pipeline
by Rodney Byles
Per Aarsleff, one of Denmarks leading civil engineering contractors, has
successfully used its extensive pipeline welding and placing expertise on its most
challenging contract so far to weld and place exceptionally heavy sections of large
diameter, extremely thick-walled cross-country gas pipeline in southwest Norway. The pipe,
which is between two to six times thicker than a conventional gas pipeline, is so heavy
and comparatively rigid that Per Aarsleff, using a combination of special beveling,
induction heating and internal and external welding equipment, can only weld a few
sections together into a short string at a time for the lifting and placing equipment to
cope with the weight.
Several separate and adjacent short strings are prepared alongside the top of the trench
ready for laying. A second Per Aarsleff team, following on behind with closely spaced
pipelaying side booms and crawler cranes, lift and lower the short sections of pipeline in
turn into the excavation. Each is butt-welded to the mating string and the welds covered
with a heat-shrinking protective sleeve. The cross-country sequence is repeated to the
edge of the fjords for the sea crossings. Here, the pipes are welded to the
concrete-coated ballasted pipeline which has been pulled across and placed on the bed of
the fjord. Per Aarsleff has played the key role in welding, pulling and laying the
pipeline across four fjords up to 2.3-km wide and depths of 84 meters.
The approximate 30-km cross country pipeline forms part of the Norwegian state-owned oil
and gas producer Statoils massive NKr7,200M Äsgard Transport and NKr6,700M Europipe
11 combined gas trunkline project. The vast scheme, one of the offshore worlds
largest and most technically challenging projects, connects the Äsgard gas field in the
northern North Sea, about 300 km northwest of the Norwegian westcoast port of Trondheim,
with the German North Sea coast at Dornum.
Sour gas will be transported from Äsgard through a 730-km long subsea pipeline to the
Norwegian landfall at Karsto on the island of Karmy, just south of Haugesund. From Karsto
the pipeline goes overland, including crossing three fjords, to Statoils existing
Karsto refinery, which is being expanded to cope with the additional supply. At Karsto,
the refined gas is transferred into the 650-km Europipe 11 trunkline. This initially
crosses two fjords and two islands en route to the Norwegian southwest coast at
Trosnavgneset, for the remaining subsea trunklink to a receiving station at Dornum and
onward distribution throughout Germany, Austria and The Netherlands.
Per Aarsleff is part of the joint venture Kaarstoe Pipeline Contractors, which includes
Selmer of Norway and the German firms Bolen & Deyen and Ludvik Freytag, working for
client Statoil on the approximate NKr900M cross-country pipeline contract. Before Per
Aarsleff could start on the cross-country welding, the site team spent several weeks
testing and evaluating different welding materials to ensure that the pipes, which were
made by different manufacturers, were compatible and could be welded together and comply
with Statoils specification to cope with the corrosive untreated gas.
Each individual pipe up to 14.25 meters long and weighing approximately one ton per meter,
is delivered from the sites stockyard to its exact position above the previously
excavated trench. The one-meter internal diameter pipe sections, which have a wall
thickness ranging from 39-mm to 55-mm depending on their location, are prepared for
welding by initially chamfering each end using a special mobile lathe. The self-contained,
hydraulically operated machine tool clamps itself onto the ends of the pipes to cut the
desired bevel to accept the butt weld.
After machining, induction heating coils are placed on the ends of two mating pipe
sections and heated to 120 degrees C prior to butting together to accept an initial
internal tacking and sealing weld. Per Aarsleff uses a special compressed air controlled,
remotely operated robot to perform this semi-automatic operation. The internal Mig welding
machine is first placed in one end of a pipe section and driven along inside to the other
end and rigidly clamped at the joint position, using a set of integral expanding clamping
pads forced out against the pipe wall. The adjacent section of pipe is lifted by one of
Per Aarsleffs pipelayers and fed over the welding machines nose protruding
from the end of the pipe. A second set of pads in the welders nose clamp hold the
two pipes together in preparation for welding. The welding machine, complete with six
welding heads, quickly completes the internal circumferential sealing weld.
Both sets of clamps are released and the internal welding machine driven along the pipe to
the next joint to repeat the sequence. At the same time, a protective cabin is placed over
the outside of the first joint. Working inside the cabin, a pair of welders clamp a
special semi-automatic twin-headed pulse Mig welding machine around the circumference of
the pipe and then fill the bottom of the V-shaped void with an initial three-pass weld.
This provides a sturdy joint for the pipes to be supported on blocks and pipelayers
released for supporting the next adjacent pipe.
This first cabin and team of two welders is moved along the pipe to the next joint which
has been previously sealed with the internal welding machine. A second cabin is placed
over the first joint and a second team of welders, using a similar semi-automatic pulse
Mig welding clamped to the pipe, complete a further three-pass weld. This sequence is
repeated at the next joint and a third cabin placed over the first joint, which is then
completed with about seven to eight passes of flux core weld. The completed butt weld is
x-rayed and approved prior to placing a heat shrinking protective sleeve over the finished
joint.
The entire cycle of front-end welding operations is repeated to weld six pipe sections
together into a single string. Per Aarsleff assembles an average three strings per day
ready for placing into the adjacent pre-dug trench. Following closely behind are
Caterpillar, Komatsu and Terex pipelayers, together with various crawler cranes, lifting
and lowering each string in turn into the trench. Each string is temporarily supported by
the pipelayers, while the two adjacent lengths of pipeline are welded together prior to
final lowering and backfilling. The entire sequence is repeated along the pipeline with
Per Aarsleff completing an average 200 meters per day. P&GJ
Rodney Byles is a veteran technical writer based in the
United Kingdom. A second story concerning the unique underwater pipe pulling aspects of
this project will be published in an upcoming issue of P&GJ. |